Learn More Below

Notice of Non-Binding Open Season

Opens at 12:00 PM CST, Wednesday, February 21, 2018
Closes at 4:00 PM CST, Friday, April 6, 2018

Haynesville Global Access Pipeline LLC (“HGAP”), a subsidiary of Tellurian Inc., is proposing to construct, own and operate an approximately $1.4 Billion with ~200-miles 42-inch diameter pipe. This proposed pipeline will be capable of transporting upwards of 2 Billion cubic feet of natural gas per day from supply sources originating in the Haynesville / Bossier Shale area.

The pipeline will consist of:

  • 1 compressor Station – approximately 23,000 HP
  • 200 miles 42-inch diameter pipe
  • 18 Meter Stations
  • 7.1 Bcf/d receipt capacity
  • 3.7 Bcf/d delivery capacity

HGAP At-A-Glance


We are a team of industry experts who have global and local experience. Our team members have previously worked on many of the contemporary pipeline projects operating throughout the world. We will put our expertise, knowledge of the community and regulatory process to good use in developing this project.


In addition to our own skills and capabilities, we have strong relationships with world renowned equipment suppliers, engineering firms, and construction contractors. The collective team is committed to operating within best practices for the safety of the community and environment.

Project Schedule

Hold Open Season Q1 2018

Customer engagement and PA negotiations

Pre-File with FERC Jan 2019

Detailed design and engineering

Major materials and ROW procurement

Receive FERC Certificate

Start construction

Project in-service

Proposed HGAP route